Will Kamoa-Kakula Project 95 be fully commissioned by 2026-12-31?
11
Ṁ10kṀ45k
Dec 31
73%
chance

Resolves YES if Ivanhoe Mines has officially confirmed that the Project 95 concentrator upgrades at Kamoa-Kakula are complete and circuits are operating at or near the target 95% copper recovery rate, as stated in a press release, quarterly report, or investor communication before December 31, 2026. Resolves NO otherwise.

Context: Project 95 upgrades the Phase 1 and Phase 2 concentrators from 87% to 95% copper recovery — an 8-point improvement translating to roughly 33,000 additional tonnes of copper per year. As of early April 2026, the project was approximately 75% complete. Commissioning may occur in stages.

Market context
Get
Ṁ1,000
to start trading!
Sort by:
bought Ṁ4,000 NO

@prismatic I think this shouldn't resolve yet. Resolution requires circuits operating at or near 95% recovery

@Simon74fe hm good point, they did already project "recoveries are expected to increase to approximately 95% over time" (https://www.investing.com/news/transcripts/earnings-call-transcript-ivanhoe-mines-q2-2026-revenue-miss-offsets-stronger-output-93CH-4825513) in last year's guidance and the earnings call today was quite positive